For a couple of years now, I've used a diagram created in an Excel spreadsheet to explain to new team members how the various Scrum time boxes interact. Here's a screenshot (click to enlarge it):
The columns in the SPRINT portion of the diagram represent work days. It should be noted that a Scrum work day doesn't necessarily start in the morning -- it starts with the Scrum.
Feel free to use this image in your team training.
If you don't recognize the "Story Sizing" ceremony, it's something we do a bit differently from traditional Scrum, but that has been adopted by many organizations. We came into it organically before I saw mention of it in other Scrum literature. Perhaps that will be the topic of a future Scrum Now!